This project, the first for St Mary’s School, involved the demolition of an existing classroom block and construction of a new 2 storey 6th Form Study Centre incorporating ICT suites, seminar & study rooms, a common room and toilet facilities.

The new structure comprised of concrete pad and strip foundations, supporting a structural steel frame bearing the precast concrete floor slabs, internal concrete staircase and profiled metal roof deck together with a ground floor block and beam suspended floor slab.

The building envelope was finished externally in a combination of facing brickwork, curtain walling, timber cladding and a through colour render system. The external walls were insulated with a profiled metal roof deck with the Parapet walls finished with an aluminium coping system with thermally broken aluminium windows, doors and a curtain wall system.

All existing gas and water mains were extended to serve the building. A new electrical supply was run from the existing substation at the school entrance into the switch room on the ground floor to serve power and lighting throughout the building.

Project Overview

Client Governors of St Mary's School
Value £2,100,000
Duration Jun 2015 - Mar 2016
Contract Type JCT 2011 Design & Build

Architect

TP Architects

Quantity Surveyor

Total Support

Structural Engineer

Chiltern Design

Services Consultant

Clearsprings Energy Solutions