Project Information

  • Client: Felsted School
  • Contract Value: £4,700,000
  • Project Duration: August 2013 - October 2014
  • Contract Type: JCT 2011

Professional Team

  • Architect: BHM Architects
  • Quantity Surveyor: Synergy Surveyors
  • Structural Engineer: David Osbourne Associates
  • Mechanical Consultant: FG Alden (Heating) Ltd

This project entailed the construction of a new girl’s facility, Follyfield House to replace the existing which was damaged extensively by fire in July 2012.

Accommodating 62 girls, the house has spacious common rooms, a well-equipped kitchen, study and relaxation areas. An open atrium spans the 3 floors of the building, overlooked by social areas on each floor. Under-floor heating connected to an air source heat pump ensures the building is environmentally friendly, and state of the art security systems control access.

The 3 storey building which comprises brick and block walls with pre cast concrete floors and a pitched slated roof has 33 single and 8 double bedrooms all with en-suite facilities.